Reorder Point & Safety Stock Calculator

Calculate the reorder point and safety stock for a target service level, from demand and lead time variability.

Updated · Free · Runs in your browser

units
units
days
days
units
US$
% of unit cost
Reorder point —
Safety stock —
Demand during lead time —
Days of stock on hand —
Reorder now? —
Value of safety stock —
Yearly cost to hold safety stock —
    Was this calculator helpful?

    The formula

    Lead-time demand = average daily demand × average lead time
    
    Safety stock:
    demand and lead time vary: Z × √(L × σd² + d² × σL²)
    demand varies only: Z × σd × √L
    
    Reorder point = lead-time demand + safety stock
    Z = service-level factor (95% → 1.645, 99% → 2.326)
    d = daily demand, σd = its standard deviation, L = lead time in days, σL = its standard deviation

    Worked example

    1. You sell an average of 40 units a day (standard deviation 8), and supplier lead time averages 10 days (standard deviation 2).
    2. Lead-time demand = 40 × 10 = 400 units.
    3. For a 95% service level (Z = 1.645): safety stock = 1.645 × √(10 × 8² + 40² × 2²) = 1.645 × √7,040 = 138.02, rounded up to 139 units.
    4. Reorder point = 400 + 138.02 = 538.02, so 539 units.
    5. With 600 units on hand (15 days of stock), you're about 1.5 days from needing to reorder.

    What the reorder point is

    The reorder point (ROP) is the stock level at which you should place a new order, so the delivery arrives before you run out. It covers the demand expected during the supplier's lead time, plus a safety stock buffer for when demand is higher or delivery is slower than average. When inventory falls to the reorder point, you order. Many inventory systems and spreadsheets trigger purchase orders automatically at this level.

    Why safety stock matters

    Without safety stock, you'd run out roughly half the time, whenever demand during the lead time is above average or the shipment is late. Safety stock absorbs that variability. The more variable your demand and lead times, and the higher the service level you want, the more you need. It's a trade-off: more safety stock means fewer stockouts and lost sales, but more money tied up in inventory and higher storage costs.

    Choosing a service level

    The cycle service level is the probability of not running out during a replenishment cycle. It sets the Z factor:

    • 90% → Z = 1.28
    • 95% → Z = 1.645 (a common default)
    • 97.5% → Z = 1.96
    • 99% → Z = 2.33
    • 99.9% → Z = 3.09

    Safety stock rises steeply at high service levels: going from 95% to 99% raises it by about 41%. Use higher levels for best-selling or critical items and lower levels for slow movers. Many businesses classify stock (ABC analysis) and set different levels for each class.

    Getting the inputs

    Calculate average daily demand and its standard deviation from at least a few months of sales history, using the same time unit as your lead time. In a spreadsheet, use AVERAGE and STDEV on daily sales. Track lead times from order to receipt for recent purchase orders and calculate their average and standard deviation. If your supplier is very reliable, choose the demand-only method; if lead times vary, use the combined formula, which accounts for both.

    The formula assumes demand is stable around an average. If sales are seasonal or growing, recalculate the reorder point regularly using recent or forecast demand, for example monthly, and raise it ahead of peak seasons. For promotions and product launches, plan stock separately. Historical averages won't capture a planned spike.

    Reorder point and order quantity

    The reorder point tells you when to order. The economic order quantity tells you how much to order to minimise ordering and holding costs. Used together, they form a simple continuous review inventory system. Also consider supplier minimum order quantities, container sizes (see the CBM calculator) and volume discounts.

    Cost of safety stock

    The calculator shows the value of your safety stock and its yearly holding cost: capital, storage, insurance, obsolescence and shrinkage, often 20–30% of the unit cost a year. Compare that with the profit lost from stockouts. Use the profit margin calculator to find profit per unit, and decide whether a higher service level pays for itself. Keep a record of every stockout too, so you can check whether your chosen service level is being achieved in practice. Review safety stock levels whenever you change suppliers, because a new supplier's lead time and reliability can be very different from the old one's.

    Frequently asked questions

    How do I calculate the reorder point?
    Multiply average daily demand by the lead time in days, then add safety stock. With 40 units a day, a 10-day lead time and 139 units of safety stock, the reorder point is about 539 units.
    What is the safety stock formula?
    For variable demand and lead time: Z × √(lead time × demand variance + average demand² × lead time variance). For variable demand only: Z × demand standard deviation × √lead time.
    What service level should I use?
    95% is a common default. Use higher levels (98–99%) for critical or high-margin items and lower ones for slow-moving or low-value items.
    What is the difference between reorder point and safety stock?
    Safety stock is a buffer for unexpected demand or delays. The reorder point is the total level at which to order: expected lead-time demand plus safety stock.
    How often should I recalculate the reorder point?
    At least every few months, and more often for seasonal products or when demand or supplier lead times change.

    ↑↓ to navigate · Enter to open