The formula
Volume = length × width × compacted thickness × (1 + waste)
Weight = volume × density
US tons = lb ÷ 2,000 · metric tonnes = kg ÷ 1,000
Hot-mix asphalt density ≈ 145 lb/ft³ (2,320 kg/m³) compacted
Tons per sq ft at 1 in ≈ 145 ÷ 12 ÷ 2,000 = 0.006
Worked example
- A driveway is 50 ft long and 12 ft wide, paved 3 in thick.
- Area = 50 × 12 = 600 sq ft.
- Volume = 600 × (3 ÷ 12) = 150 cu ft, plus 5% waste = 157.5 cu ft (5.83 cu yd).
- Weight = 157.5 × 145 lb = 22,838 lb, or 11.4 US tons (10.4 tonnes).
- At $110 a ton, the asphalt costs about $1,256, and the whole order fits on one truck.
How asphalt is ordered
Hot-mix asphalt (HMA), also called blacktop, tarmac or bitumen macadam, is made from crushed stone, sand and about 5–6% bitumen binder, mixed at around 150 °C (300 °F). Plants sell it by weight, in US tons or metric tonnes, so you need to convert the area and thickness of your job into weight. The calculator multiplies the volume by the compacted density, about 145 lb per cubic foot or 2,320 kg per cubic metre for typical dense-graded mixes. Asphalt is laid loose and then compacted by about 20–25% with rollers, so always use the finished, compacted thickness in the calculation.
Choosing the thickness
- Footpaths and garden paths: 1½–2 in (40–50 mm).
- Residential driveways: 2–3 in (50–75 mm) compacted, often as a single layer, or a 2 in base course with a 1 in surface course.
- Driveways with heavy vehicles such as RVs or delivery trucks: 3–4 in (75–100 mm).
- Car parks and roads: designed by an engineer, often with 4–6 in or more in several layers.
The asphalt is only as good as what's under it. A well-drained, compacted base of crushed stone, typically 4–8 in (100–200 mm) for driveways and more on soft clay, does most of the structural work.
Waste and thickness variation
Real surfaces are never perfectly flat, so the asphalt crew fills low spots in the base, and some material is lost at edges, joints and the end of each truckload. A 5% allowance is typical for well-prepared jobs; use 8–10% for uneven bases or small, irregular areas. Order slightly more rather than less, because a second delivery to cover a shortfall can cost almost as much as the first and leaves a visible joint.
Hot weather, cold weather
Asphalt must be laid and compacted while it's hot, so paving usually stops when air or ground temperatures fall below about 40–50 °F (5–10 °C). It cools quickly in wind and on cold ground, so thin layers are harder to compact in cool weather. Fresh asphalt is soft for several days in hot weather: avoid turning wheels on the spot, parking in the same place or using stands and jacks on it for the first few days. A sealcoat applied after 6–12 months and every few years after that helps protect it from oxidation, water and oil.
Sealcoating and repairs
Asphalt oxidises and becomes brittle under sun and rain. A sealcoat, a thin protective layer of coal-tar or asphalt emulsion, slows this and restores the dark colour. Wait at least 6–12 months before the first coat so the surface can cure, then reseal every two to four years. Fill cracks wider than about ⅛ in (3 mm) with a hot or cold crack filler before winter to stop water getting in and freezing. Potholes should be cut back to sound material and patched with hot or cold mix, compacted firmly.
Costs and alternatives
Asphalt mix prices vary with oil prices and location, commonly $90–150 per ton in the US and £70–120 per tonne in the UK, before laying. Installed costs for a new residential driveway are often $3–7 per sq ft, including base preparation and labour. Concrete costs more but lasts longer and needs less maintenance; gravel is the cheapest option. Compare materials with our concrete calculator and gravel calculator, and check the driveway gradient with the slope calculator.