Cut and Fill Earthwork Calculator

Estimate cut and fill volumes for levelling a site from a grid of spot elevations, with swell, compaction shrinkage, truckloads and the balance level.

Updated · Free · Runs in your browser

Units
ft
ft

Existing ground heights at evenly spaced grid points, separated by commas, in ft or m.

In the same units as the spot heights.

%

Loose volume increase when dug: about 10–15% sand, 25% common earth, 30–40% clay, 50%+ rock.

%

Extra in-place material needed because fill compacts: typically 10–20%.

Net earthwork —
Cut (bank volume) —
Fill (compacted) —
Fill material needed (bank volume) —
Cut after swell (to haul) —
Truckloads —
Level that balances cut and fill —
Area per point —
    Was this calculator helpful?

    The formula

    Area per grid point = site area ÷ number of points
    At each point, depth = existing elevation − target elevation
    Cut = Σ positive depths × area per point
    Fill = Σ |negative depths| × area per point
    Fill material needed = fill × (1 + shrinkage)
    Loose cut to haul = cut × (1 + swell)
    Net = cut − fill material needed
    Balance level = average of all spot elevations

    Worked example

    1. A 60 × 40 ft pad (2,400 sq ft) has 12 spot heights from 99.1 to 101.2 ft, and the target level is 100.2 ft.
    2. Each point represents 2,400 ÷ 12 = 200 sq ft.
    3. The six points above 100.2 ft are 3.2 ft too high in total, so the cut is 3.2 × 200 = 640 cu ft (23.7 cu yd).
    4. The points below total 2.9 ft, so the fill is 2.9 × 200 = 580 cu ft (21.5 cu yd).
    5. Allowing 15% compaction, the fill needs 580 × 1.15 = 667 cu ft (24.7 cu yd) of material.
    6. Net: 640 − 667 = −27 cu ft, so about 1 cu yd must be imported. The average spot height, 100.22 ft, is the level that would balance cut and fill.

    What cut and fill means

    When a site is levelled for a building pad, driveway, patio or sports field, soil is dug out where the ground is too high (cut) and placed where it's too low (fill). Estimating these volumes before you start lets you choose a finished level that keeps earthwork to a minimum, plan how many truckloads of soil to haul away or bring in, and price the job. Earthworks are often one of the most uncertain costs on a project, and moving soil within the site is far cheaper than importing or exporting it.

    The grid method

    This calculator uses the grid (or borrow-pit) method. Lay out a regular grid of points over the site, for example every 10 ft or every 3 m, and measure the existing ground level at each one with a laser level, a dumpy level and staff, or a GPS rover. Each point then represents an equal share of the total area. The difference between each spot height and the target level, multiplied by that area, gives the cut or fill at that point. The more points you take, the more accurate the result, especially on uneven ground. For long roads, trenches and embankments, engineers use cross-sections and the average-end-area method instead.

    Swell and shrinkage

    Soil changes volume when it's dug and compacted. Undisturbed soil in the ground is called bank volume. When excavated, it breaks up and swells: about 10–15% for sand and gravel, 20–30% for common earth, 30–40% for clay and 50% or more for blasted rock. Trucks are loaded by loose volume, so the swell factor determines how many loads you need. When fill is spread and compacted in layers, it becomes denser than it was in the ground, typically by 10–20%, so you need more bank volume of fill than the space it fills. Ignoring shrinkage is a common reason why sites end up short of fill.

    Choosing the finished level

    The level that balances cut and fill is roughly the average of the spot heights, before allowing for shrinkage. In practice, designers also consider drainage, with ground falling away from buildings at 5% or more for the first 10 ft (3 m); access, so driveways aren't too steep; topsoil, which is usually stripped and stockpiled separately because it's unsuitable as structural fill; and the soil type. Fill under buildings and slabs should be placed in thin layers, typically 6–8 in (150–200 mm), and compacted to the specified density. Our slope calculator checks drainage falls and driveway grades.

    Soil types and compaction

    Not all excavated soil is suitable for fill. Clean granular materials such as sand and gravel compact well and drain freely, while clay can be used if it's placed at the right moisture content and compacted in thin layers. Organic soils, peat and topsoil should never be used under buildings, slabs or roads because they decay and settle. Compaction is usually specified as a percentage of the maximum dry density from a Proctor test, often 95% for structural fill, and checked on site with a nuclear density gauge or sand-cone test.

    From volume to cost

    Earthwork is usually priced per cubic yard or cubic metre, with separate rates for excavation, hauling, imported fill and compaction. A standard US tandem dump truck carries about 10–14 cu yd of loose soil; in the UK and Europe, an 8-wheel tipper carries around 20 tonnes or 7–10 m³. Disposal of excavated soil can be expensive, especially if it's contaminated, so balancing cut and fill on site saves money. For gravel to finish the levelled area, use our gravel calculator, and for slabs on the finished pad, the concrete calculator.

    Frequently asked questions

    How do I calculate cut and fill?
    Measure existing levels on a grid, subtract the target level at each point, multiply each difference by the area each point represents, and add the positive values (cut) and negative values (fill) separately.
    What is the swell factor for soil?
    About 10–15% for sand and gravel, 25% for common earth, 30–40% for clay and 50% or more for broken rock. Swell is the increase in volume when soil is dug out.
    Why do I need more fill than the hole I'm filling?
    Fill compacts when it's rolled in layers, typically by 10–20%, so you need more loose or bank-volume material than the final compacted space.
    How many cubic yards are in a dump truck?
    A standard US tandem dump truck carries about 10–14 cu yd of loose material; smaller single-axle trucks carry 5–6 cu yd.
    How can I reduce earthwork costs?
    Choose a finished level close to the balance level so cut on site supplies the fill, keep topsoil separate for reuse, and avoid exporting or importing soil where possible.