The formula
Volume = length × width × thickness × quantity × (1 + waste %)
Imperial: ft × ft × (in ÷ 12) = ft³; ft³ ÷ 27 = yd³
Metric: m × m × (cm ÷ 100) = m³; 1 m³ ≈ 1.308 yd³
Bag yield: 80 lb ≈ 0.60 ft³ · 60 lb ≈ 0.45 ft³ · 25 kg ≈ 0.0117 m³
Worked example
- A 10 ft × 10 ft patio slab, 4 in thick.
- Volume = 10 × 10 × (4 ÷ 12) = 33.33 ft³.
- Add 10% waste: 33.33 × 1.10 = 36.67 ft³.
- In cubic yards: 36.67 ÷ 27 ≈ 1.36 yd³.
- 80 lb bags: 36.67 ÷ 0.60 ≈ 61.1, so buy 62 bags. Or order about 1.5 yd³ of ready-mix, since suppliers often sell in ¼ or ½ yard steps.
- At $150 per yd³, the ready-mix cost ≈ 1.36 × 150 ≈ $204, plus any delivery or short-load fee.
How to calculate concrete volume
Concrete is ordered by volume: cubic yards in the US, and cubic metres in the UK, Canada, Australia, India and most other countries. For any rectangular pour, such as a slab, patio, driveway, shed base or strip footing, multiply length × width × thickness, with all three in the same unit. The most common mistake is mixing units, for example multiplying feet by inches. Convert inches to feet by dividing by 12 (4 in = 0.333 ft), or centimetres to metres by dividing by 100.
For several identical pours, such as fence-post footings or deck piers, enter the quantity. For an irregular shape, break it into rectangles, calculate each one and add them up. For round columns or piers, use π × radius² × height.
How thick should a slab be?
- Walkways, patios, shed bases: typically 4 in (100 mm).
- Driveways for cars: 4–5 in (100–125 mm). Use 5–6 in (125–150 mm) for heavier vehicles such as trucks, RVs and vans.
- Garage floors: commonly 4–6 in, depending on use and local code.
- Footings and foundations: set by structural design and local building codes, often 8–12 in or more. Always follow the engineer's or building official's specification.
A well-compacted sub-base of gravel or hardcore, typically 4–6 in (100–150 mm), is just as important as concrete thickness for preventing cracks. Our gravel calculator can size it.
Bags or ready-mix?
Premixed bags are convenient for small jobs such as post holes, small pads and repairs. An 80 lb (36 kg) bag yields about 0.6 cubic feet, so one cubic yard takes about 45 bags. That's a lot of mixing. As a rule of thumb, for more than about 1 to 1.5 cubic yards (around 1 m³), a ready-mix truck is usually cheaper, faster and gives a more consistent result. Ask about minimum orders and short-load fees, which can apply to small deliveries, and make sure the truck can reach your site or book a concrete pump.
Prices vary widely by region, season and mix strength. Enter your local price per cubic yard or cubic metre to estimate the cost.
Why add a waste allowance?
The ground is never perfectly level, forms bow slightly, some concrete sticks to the mixer and wheelbarrow, and a little is always spilled. Running short mid-pour can create a weak "cold joint", so contractors typically order 5–10% extra. Use the higher end if your sub-base is uneven or you're pouring by hand. Leftover concrete can be used for a small pad or stepping stones, so plan for it before the truck arrives.
For structural elements such as foundations, retaining walls and suspended slabs, reinforcement, mix design and curing matter as much as volume. Consult a qualified professional and check local building codes.
Mixing, placing and curing
Getting the quantity right is only the first step. For a strong, crack-resistant slab:
- Don't add extra water to make concrete easier to work. Too much water is the most common cause of weak, dusty, cracked concrete. Follow the bag or supplier's water ratio.
- Place and finish promptly. On hot, dry or windy days concrete sets faster, so have enough helpers and tools ready before the pour.
- Add control joints to guide where cracking happens. A common rule is to space them no more than 2–3 times the slab thickness in feet (for example, every 8–12 ft for a 4 in slab) and cut them about a quarter of the slab's depth.
- Cure it. Keep the surface moist for at least 7 days by covering it with plastic sheeting, wet burlap or a curing compound. Concrete keeps gaining strength for weeks and reaches its design strength at about 28 days.
- Protect from frost. Don't pour onto frozen ground, and protect fresh concrete from freezing for the first few days.